13 August 2025 - Solar Panel Installation









25 July 2025 - Passed Final Inspection





29 June 2025 - Finishes











27 May 2025 - Metal Roof Installation, Kitchen, and Finishes.









07 May 2025 - Tile - In addition to the ADU, we are currently building the SHED to house the laundry, bicycles, and tools.








30 April 2025 - Plaster




















29 April 2025 - Plaster










24 April 2025 - Plaster

















09 April 2025 - Install Windows, AC, Vent fans, etc.







22 March 2025 - Connect Sewer Line & Graywater Line with Diverter Valve






18 March 2025 - Install Solar Panel Infrastructure.





13 March 2025 - Passed intermediate inspections.








5 February 2025 - Electric








18 February 2025 - Roof Framing and Plumbing Rough


















29 January 2025 - Second Grout Pour














20 January 2025 - First grout pour







08 January 2025 - 8' stacked for first grout












02 January 2025 - Concrete Pour













28 December 2024 - Pre-Slab inspection passed




12 December 2024 - First inspection passed - Rough Soil













25 November 2024 - Permit approved and marking of the footprint for the Detached Sonoran ADU in preparation for digging footers.